Activity:

User Acceptance Testing (CMMI Level 3 : VAL 2.1 )

Participating Roles

Responsible:

Tester

User Experience Architect

Accountable:

Test Manager

Informed:

Release Manager

Overview

Entry Criteria

  • Tests written to validate the customer requirements.
  • Procedures for running and reporting user acceptance tests.
  • A build which has passed user acceptance test criteria and is now considered a release candidate.

Sub-Activities

1

Run User Acceptance Tests

  • Run a series of tests defined for the functionality in release candidate build.

2

Report Results

  • Test results including bug reports from failed tests and change requests from exploratory testing activities.

Exit Criteria

Test results including bug reports and change requests.