Activity:
Plan Product Integration (CMMI Level 3 : PI 1.1 )
|
|
Participating Roles
Responsible:
Architect
Build Engineer
Accountable:
Architect
Consult:
Developer
Informed:
Development Manager
Developer
Test Manager
Tester |
Product integration planning consists of creating the integration sequence and the defining criteria to be met prior to integration. Incremental integration and testing creates a stable foundation upon which other functionality can be integrated.
Entry Criteria
When:
- After significant updates to the solution architecture, typically once at the beginning of each iteration.
Dependencies:
- Solution Architecture Complete: The solution architecture has been created and approved.
Sub-Activities
|
1 |
Plan Integration Sequence |
- Create the integration sequence. Sequencing depends on factors such as dependencies (which functionality needs to be integrated at the same time, before, or after other functionality), availability, and risk.
|
2 |
Establish Integration Criteria |
- Create the criteria to be met prior to integrating code. Typical criteria include unit test reports, peer reviews, and passing code analysis tool tests.
|
3 |
Review Integration Plan |
- Review, revise, and approve the product integration planning.
|
Exit Criteria
|
The sequence and criteria for product integration are planned. | |
|
|
|
|