Activity:

Verify Integration Environment (CMMI Level 3 : PI 1.2 )

Participating Roles

Responsible:

Architect

Build Engineer

Accountable:

Architect

Consult:

Developer

Informed:

Development Manager

Developer

Test Manager

Tester

Overview

Entry Criteria

    When:

    • After significant updates to the solution architecture, typically once at the beginning of each iteration.

    Dependencies:

    • Integration Environment Established: The integration environment is established.

    Sub-Activities

    1

    Verify Environment

    • Verify that the integration environment is appropriate for the project. Check to see that all elements of the environment have been addressed. Compare the environment to the product integration plan to see if any issues or elements have been overlooked.

    Exit Criteria

    The integration environment is verified to be appropriate for the project.