Activity:
Verify Integration Environment (CMMI Level 3 : PI 1.2 )
|
|
Participating Roles
Responsible:
Architect
Build Engineer
Accountable:
Architect
Consult:
Developer
Informed:
Development Manager
Developer
Test Manager
Tester |
The integration environment should be appropriate for the development environment and address the issues and needs set forth in the product integration plan.
Entry Criteria
When:
- After significant updates to the solution architecture, typically once at the beginning of each iteration.
Dependencies:
- Integration Environment Established: The integration environment is established.
Sub-Activities
|
1 |
Verify Environment |
- Verify that the integration environment is appropriate for the project. Check to see that all elements of the environment have been addressed. Compare the environment to the product integration plan to see if any issues or elements have been overlooked.
|
Exit Criteria
|
The integration environment is verified to be appropriate for the project. |