MSF for CMMI Process Improvement Visual Studio Team System logo

Activity:

Take Corrective Action (CMMI Level 2 : PMC 2.2 )

Participating Roles

Responsible:

Project Manager

Accountable:

Project Manager

Overview

Entry Criteria

  • A list of task work items designed to resolve the source issue.

Sub-Activities

1

Resolve Tasks

  • Undertake the task, complete it, and update the work item as resolved.

2

Insure Source Issue Resolution

  • Does the completion of the task in the previous step resolve the source issue? If not, why not? Are there other outstanding tasks? If so, then wait for these to complete. Otherwise, do additional tasks need to be added to the corrective action plan?

3

Insure Flow

  • Can the blocked work items be restarted? If not, are there other issues that need to be raised or do some of the corrective action plan tasks require rework?

Exit Criteria

An updated list of tasks.

(C) 2005 Microsoft Corporation. All rights reserved.

MSF for CMMI Process Improvement: Build 050707