Based on the proposed iteration backlog, the skills analysis, and the reports from previous iterations, make an estimate of the required resources to complete the iteration within the anticipated schedule.
Entry Criteria
The proposed list of tasks of the iteration.
Project reports from previous iterations.
A list of the required skills to complete the iteration.
A plan describing the required involvement of stakeholders to complete the iteration.
Sub-Activities
1
Estimate Iteration Resources
Use the previous iteration reports, the proposed iteration backlog, and the required skills analysis to make an estimate of the team size naming any specific individuals with specialist required skills.
Exit Criteria
A list of the required resources that may also include named individuals.