Activity:

Monitor Data Management (CMMI Level 2 : PMC 1.4 )

Participating Roles

Responsible:

Project Manager

Accountable:

Project Manager

Consult:

Any

Informed:

Auditor

IPM Officer

Development Manager

Test Manager

Overview

Entry Criteria

  • A plan agreed upon for project data collection and storage procedures.
  • Team System data warehouse project data.

Sub-Activities

1

Review Data Collection and Storage Against Plan

  • Analyze the usage of Team System across the project team. Compare collected data against the agreed upon project data collection plan.
  • Compile a report of any deviation from plan.

2

Consider Corrective Action

  • Optional
  • Consider any corrective action required to bring the data collection and storage into alignment with the plan or any changes to the plan which are needed to reflect operational reality.

Exit Criteria

A report of the conformance or deviation from plan.

Suggested corrective action to bring the collection and storage procedures into alignment with plan or amendments to the plan to better reflect operational reality.