MSF for CMMI Process Improvement Visual Studio Team System logo

Activity:

Identify Inconsistencies (CMMI Level 2 : REQM 1.5 )

Participating Roles

Responsible:

Business Analyst

Accountable:

Business Analyst

Consult:

Any

Informed:

Project Manager

Development Manager

Test Manager

IPM Officer

Overview

Entry Criteria

  • The set of scenarios, qualities of service, and all other product requirements for the project.
  • The project plan including all commitments, schedule, and budget.
  • The project reports from the project portal (and data warehouse).

Sub-Activities

1

Compare Work Done Against Work Planned

  • For both the current iteration and the project as a whole, take the originally committed requirements and project plan and compare them to the actual events.
  • Use the iteration and project reports in the project portal as evidence of actual work done.

2

Identify Variance

  • Identify where the actual work done varies from the plan and original commitment. Note the size of the variation.
  • For example, if plans were made based on a velocity of 2 scenarios per developer per week, and actuals reflect that only 1.8 scenarios per week was achieved, the variation in velocity is -0.2 or -10%.
  • Variations in all the project plan commitments such as scope and schedule as well as all the project metrics reflected in the standard reports e.g. Unplanned Work, should be compiled.

3

Report Variation

  • Report the variation in actual work against plan.

Exit Criteria

(C) 2005 Microsoft Corporation. All rights reserved.

MSF for CMMI Process Improvement: Build 050707