MSF for CMMI Process Improvement Visual Studio Team System logo

Activity:

Establish a User Acceptance Test Environment (CMMI Level 3 : VAL 1.2 )

Participating Roles

Responsible:

Test Manager

Accountable:

Release Manager

Overview

Entry Criteria

  • Notification that user acceptance testing will need to start on a given date.

Sub-Activities

1

Define Equipment and Facilities Required

  • Define the facilities and equipment required for user acceptance testing.

2

Commission Facilities and Equipment

  • Acquire and commission the facilities and equipment.  

Exit Criteria

Notification that the user acceptance test environment is ready for use.

(C) 2005 Microsoft Corporation. All rights reserved.

MSF for CMMI Process Improvement: Build 050707