Activity:

Establish User Acceptance Test Procedures and Criteria (CMMI Level 2 : GG 2.1 )

Participating Roles

Responsible:

Test Manager

Accountable:

Release Manager

Overview

Entry Criteria

  • Notification that user acceptance testing must start on a given day.

Sub-Activities

1

Establish Procedures

  • Establish a set of procedures for scheduling, developing, running, and reporting user acceptance tests

2

Establish Acceptance Criteria

  • Establish criteria for evaluating a release candidate based on its user acceptance test results.
  • Establish criteria for evaluating a user acceptance test candidate based on its system test results.

Exit Criteria

A set of procedures for running user acceptance testing including procedures for scheduling tests, writing test plans and test cases, running tests, and reporting test results.

Criteria for measuring the quality of a system tested user acceptance test candidate.

Criteria for measuring the quality of a tested release candidate.