Activity:

Determine Risk Management Strategy (CMMI Level 3 : RSKM 1.3 )

Participating Roles

Responsible:

Project Manager

Accountable:

Project Manager

Consult:

Auditor

IPM Officer

Overview

Entry Criteria

  • A project process template (generally the MSF for CMMI® Process Improvement process template).

Sub-Activities

1

Decide Whether to Customize or Not

  • Consider the Risk Management workstream and decide whether it is acceptable for your project, product and organization.
  • The standard risk management guidance includes a daily monitoring of risk parameters against identified risks, selection of risk for mitigation, mitigation action planning, and contingency planning.

2

Customize Risk Management

  • Optional
  • Customize the process template to replace the Risk Management workstream or delete it and add suitable risk management activities at other points in the process definition file.

3

Review Customized Risk Management

  • Optional
  • Together with the integrated program management (IPM) office and the auditors, review the customized risk management approach for acceptability against the Risk Management (RSKM) CMMI® level 3 process area.

Exit Criteria

If customizing the risk management strategy, then an updated process template is produced.