Activity:

Define Risk Parameters (CMMI Level 3 : RSKM 1.2 )

Participating Roles

Responsible:

Project Manager

Accountable:

Project Manager

Overview

Entry Criteria

  • A list of risk categories and their sources in the project.
  • The MSF project process definition template including work item type definitions.

Sub-Activities

1

Decide Whether to Customize or Not

  • Decide whether or not the supplied risk work item type definition is good enough.
  • Supplied default risk parameters are: description of risk, severity of impact on project commitments  if it occurs, probability of occurrence, affected area, mitigation plan, mitigation triggers, mitigation estimate, contingency plan, contingency trigger, and contingency plan estimate.

2

Determine Risk Parameters

  • Optional
  • If you wish to customize the risk work item, for each category of risk identified, define the parameters which are appropriate to measure the risk, mitigation, and contingency plans.
  • Modify the existing work item type definition.

Exit Criteria

If required, an updated process template with a new risk work item definition.