MSF for CMMI Process Improvement Visual Studio Team System logo

Activity:

Analyze User Acceptance Test Results (CMMI Level 3 : VAL 2.2 )

Participating Roles

Responsible:

Release Manager

Accountable:

Release Manager

Consult:

Test Manager

Informed:

Project Manager

Development Manager

IPM Officer

Overview

Entry Criteria

  • The criteria for evaluating a release candidate as acceptable.
  • The results from user acceptance testing.

Sub-Activities

1

Evaluate User Acceptance Test Results

  • Evaluate the user acceptance test results against the release acceptance criteria.
  • Include the CTQ factors defined at the beginning of the life cycle.

2

Summarize Results

  • Summarize the results with a recommendation for promotion to release or reject and request a new candidate.

3

Promote for Release

  • Optional
  • Promote the acceptable release candidate for release.

Exit Criteria

The build is promoted to "proposed for release."

The release candidate was unacceptable and a new candidate should be selected and retested.

(C) 2005 Microsoft Corporation. All rights reserved.

MSF for CMMI Process Improvement: Build 050707