1 |
In the task view in Microsoft Project, choose the task below the desired scenario or quality of service requirement that you wish to separate into tasks. |
2 |
From the Insert menu, click New Task. |
3 |
Enter the name of the new task in the empty row. |
4 |
Set the Work Item Type to Task. |
5 |
Set the name of the task owner in the Assigned To field. |
6 |
While the desired tasks in Iteration 0 selected, right-click and select Task Information. On the Advanced tab, change the Task type to Fixed Duration and set the Duration to the iteration length in days. |
7 |
On the Work Items menu, click Publish to create the new tasks. |
8 |