Plan an Iteration

Project Manager

Participating Roles

Responsible:

Project Manager

Consult:

Business Analyst

Architect

Developer

Tester

Overview

Entry Criteria

    Dependencies:

    • The scenario list and quality of service requirements list have been prioritized and published to the project portal.

    Activities

    1

    Determine Iteration Length

    • Work backward from the end date.
    • Check the scenario size.
    • Examine integration costs.
    • Review iteration length.

    2

    Estimate Scenario

    • Identify a subset of the scenario list.
    • Create implementation estimates.
    • Identify special needs.

    3

    Estimate Quality of Service Requirement

    • Identify a subset of the quality of service requirement list.
    • Create implementation estimates.
    • Identify constraints.

    4

    Schedule Scenario

    • Create an initial iteration plan.
    • Adjust the initial iteration plan.
    • Hold the iteration planning meeting.

    5

    Schedule Quality of Service Requirement

    • Create initial iteration plan.
    • Adjust the initial iteration plan.
    • Hold iteration kickoff meeting.

    6

    Schedule Bug Fixing Allotment

    • Schedule the bug allotment.
    • Consider dependencies and other factors.
    • Hold the iteration planning meeting.

    7

    Divide Scenarios into Tasks

    • Gather the team.
    • Create architecture and development tasks.
    • Choose architecture and development tasks.
    • Reassign the scenario.
    • Create test tasks.
    • Choose test tasks.

    8

    Divide Quality of Service Requirements into Tasks

    • Gather the team.
    • Identify architecture and development tasks.
    • Choose architecture and development tasks.
    • Reassign the quality of service requirement.
    • Create test tasks.
    • Choose test tasks.

    Exit Criteria

    The iteration plan is complete and published to the project portal.

    An appropriate amount of work is scheduled for the iteration.