Guide Iteration

Project Manager

Participating Roles

Responsible:

Project Manager

Overview

Entry Criteria

    When:

    • At the start of each iteration

    Activities

    1

    Monitor Iteration

    • Review work item priorities.
    • Resolve issues.

    2

    Mitigate a Risk

    • Reduce the probability of the risk.
    • Reduce the impact of the risk.
    • Make contingency plans.
    • Apply decisions.

    3

    Conduct Retrospective

    • Set up the retrospective.
    • Hold iteration retrospective meeting.
    • Incorporate feedback into the next iteration.

    Exit Criteria

    The iteration is completed and retrospective feedback, when necessary, has been incorporated.